Maylands House

Block of flats
Maylands House
In progress90%
Follow the progress of Major Works at Maylands House
External Facade
Start June 2023Expected to end December 2026
Status: in progress
Phase two involves improving the external facade and revamping the entry system.
This milestone includes
Erect scaffolding on Elystan Street
Start January 2025Expected to end March 2025
Like building a ladder to the sky, scaffolding gives our team safe access to every nook and cranny of the facade.
Front hoarding installation
Start January 2025Expected to end March 2025
Front hoarding installation
Raise Scaffold at the Rear
Start January 2025Expected to end April 2025
Asbestos Survey on Fabric
Start April 2025Expected to end May 2025
Before any changes, we check for asbestos, safely inspecting the fabric to ensure everything is clear and ready for the works to continue.
Windows Survey, Drawings & Order
Start May 2025Expected to end May 2025
Our team takes a careful look at the rear-facing windows, planning repairs and replacements to ensure they are functional and beautiful once again.
Clean of Exterior Walls
Start May 2025Expected to end June 2025
Using a low-pressure steam cleaning method to clean the building’s exterior.
Windows Manufacturing
Start May 2025Expected to end May 2026
Custom windows are crafted specifically for the rear elevation, perfectly fitting into the space to enhance the look and feel of the building.
Inspect and Brick Repairs
Start June 2025Expected to end June 2025
Each brick and stone is examined for wear and tear, with a strategy created to repair and re-point wherever necessary, preserving the building's history.
Stone Repairs
Start June 2025Expected to end July 2025
Stones are gently cleaned, returning the rear facade to its former glory.
Waterproofing to Stonework
Start August 2025Expected to end September 2025
Special waterproofing is applied to the building's feature stonework, protecting it from the elements and ensuring it lasts for years to come.
Install Rear Windows
Start November 2025Expected to end December 2025
New windows are carefully fitted into the rear elevation, bringing light and a polished look to the space.
Front Windows Upgrade
Start March 2026Expected to end May 2026
New windows have been carefully installed on the top floor, adding natural light and a refined finish, while the sash windows on the lower levels are set to be overhauled.
Final Check of Exterior Fabric
Start September 2025Expected to end May 2026
Once the heavy lifting is done, a thorough inspection is carried out to ensure the main exterior work is completed to the highest standards.
Striking the scaffold
Start May 2026Expected to end June 2026
Striking the scaffold is the process of safely dismantling scaffolding after construction work has been completed. The scaffold is removed systematically from the top down, with all components lowered carefully to the ground to prevent accidents or falling materials.
External fabric repairs
Start October 2026Expected to end December 2026
A final snagging check of the external fabric of every building, repairing any remaining defects and making sure nothing has been missed.