Kingsmill House

Kingsmill House

Block of flats

Kingsmill House

In progress90%

Follow the progress of Major Works at Kingsmill House

4Completed in June 2026Communal Areas
  1. Communal concrete repairsCompleted
  2. Communal concrete decorationsCompleted
  3. Communal door systemCompleted
  • Key:
  • To start
  • In progress
  • Completed

Loading video…

Communal Areas

Start August 2023Expected to end June 2026

Status: completed

During this phase, we will upgrade and improve all aspects of the shared spaces. This includes a new entry system and repairs to the outside spaces.

This milestone includes

Communal concrete repairs

Start June 2026Expected to end June 2026

Overtime any significant cracks in the concrete can allow water to corrode the steel rebar underneath. During this phase, we remove the damaged concrete before treating the rebar and then sealing the concrete above.

Communal concrete decorations

Start June 2026Expected to end June 2026

During this part of the project we will ensure the communal concrete areas remain sterile by removing any inflammable material, thus ensuring there's nothing flames can spread through.

Communal flooring

Start March 2026Expected to end June 2026

At this point we will complete a full overlay of the existing flooring bringing it back to a new standard.

Communal door system

Start August 2023Expected to end August 2023

At this stage we will install a new entrance system with Mag locks and call points to each apartment. We will install the upgraded door system and connect the call points.

Atrium roof glazing

Start March 2026Expected to end April 2026

The atrium roof glazing will be replaced, and new windows and a door will be installed to improve weather protection, insulation, and natural light.

Communal area painting

Start April 2026Expected to end June 2026

Communal area painting works are currently in progress using Euroclass B fire-rated paint to improve both the appearance and fire safety of the building. Preparation, surface repairs, and painting are being carried out in shared corridors and stairwells in accordance with health and safety requirements.