Jenningsbury House

Block of flats
Jenningsbury House
In progress90%
Follow the progress of Major Works at Jenningsbury House
Communal Areas
Start August 2023Expected to end June 2026
Status: completed
During this phase, we will upgrade and improve all aspects of the shared spaces. This includes a new entry system and repairs to the outside spaces.
This milestone includes
Communal concrete repairs
Start June 2026Expected to end June 2026
Overtime any significant cracks in the concrete can allow water to corrode the steel rebar underneath. During this phase, we remove the damaged concrete before treating the rebar and then sealing the concrete above.
Communal concrete decorations
Start June 2026Expected to end June 2026
During this part of the project we will ensure the communal concrete areas remain sterile by removing any inflammable material, thus ensuring there's nothing flames can spread through.
Communal flooring
Start April 2026Expected to end June 2026
At this point we will complete a full overlay of the existing flooring bringing it back to a new standard.
Communal door system
Start August 2023Expected to end August 2023
At this stage we will install a new entrance system with Mag locks and call points to each apartment. We will install the upgraded door system and connect the call points.
Communal lounge decoration
Start January 2026Expected to end July 2026
As part of the wider estate improvement programme, the lounge has been fully refurbished.
