Hammerfield House

Hammerfield House

Block of flats

Hammerfield House

In progressProgress not available

Landscaping is next

Follow the progress of Major Works at Hammerfield House

5In progressThe External works
  1. Rainwater replacementCompleted
  2. Soil pipe replacementCompleted
  3. Pigeon controlCompleted
  4. Exterior lightingCompleted
  5. Hard LandscapingTo start
  6. Soft LandscapingTo start
  • Key:
  • To start
  • In progress
  • Completed

Loading video…

The External works

Start November 2023Expected to end TBC

Status: in progress

From repairing the guttering, to landscaping the gardens, to pigeon-proofing the building, this phase is all about future-proofing the building.

This milestone includes

Rainwater replacement

Start November 2023Expected to end November 2023

As the title suggests, this stage of the process involves replacing any defective guttering and upgrading the existing system where required and landscaping the area to ensure rain water drains efficiently.

Soil pipe replacement

Start April 2024Expected to end April 2024

During this phase we will take care to repair and replace the building's soil and waste pipes and make sure they are functioning as intended.

Pigeon control

Start July 2024Expected to end July 2024

While pest control plays a part in many phases of the construction, at this stage we'll focus on one of London's worst pests, pigeons. To protect the building from this winged menace, we will install pigeon spikes and pigeon wire on all applicable ledges to encourage the birds to nest elsewhere.

Exterior lighting

Start November 2023Expected to end July 2024

As part of the landscape works we will be installing new exterior lighting and installing new CCTV cameras.

Final touches

Start August 2024Expected to end September 2024

Once, we reach this stage, most of the work will have been done. Now, all that's left to do is tidy up the overall building and grounds. We will tidy up any tired looking areas and add a fresh coat of paint to anything that's previously been painted.

Hard Landscaping

Start TBCExpected to end TBC

Now that the building repairs are complete, it’s time to bring in the landscapers to help it blend into its surroundings and connect it to the outside world.

Soft Landscaping

Start TBCExpected to end TBC

With the building and grounds settling into their environment, it only remains for our gardeners and landscapers to work their charm and bring some greenery to the grounds.